How Long Does a Bathroom Remodel Take in Parma, OH?

Updating a bathroom from top to bottom isn't a one-day project. Depending on the scope of the work and the kind of upgrades you want, remodeling a bathroom could take several days or weeks. So, how long does a bathroom remodel take on average?
Bathroom renovations and plumbing repairs in Parma, OH, often go hand in hand, so our Formica Plumbing & Sewer Co. team has experience with bathroom remodeling. If you're ready to update your space, consult our post below to understand the average timelines for various aspects of the remodeling process.
What To Expect With a Professional Bathroom Remodel in Parma
Before answering questions like "How long does a bathroom remodel take?" it helps to know what professional remodels entail. A full remodel isn't like changing the wall color with new paint or updating the room's decor. Proper remodeling takes extensive planning.
1. Creating the Design and Budget
Before starting any remodeling project in Parma, you must first develop a design and a budget. This phase will take time. It involves consultations with the plumber or general contractor, architectural drawings, design planning, and labor and cost estimations.
2. Estimation
The initial rough estimates will become more accurate as the planning continues. Reputable contractors in Parma will adjust the final cost by narrowing it down or expanding it, depending on your decisions regarding the finalized plans. During the estimation stage, the contractor will provide a construction contract with your project's fixed price and details about the work the team will provide.
3. Finalizing Construction Plans
It could take two to eight weeks for the construction or plumbing team to finalize construction plans. During this time, they will apply for permits for bathroom renovation, order materials, book subcontractors, and outline the project's schedule, including start times and deadlines. It isn't until after they finalize construction plans that the actual remodeling work begins.
How Long Bathroom Remodels Take
How long does a bathroom remodel take in Parma once it reaches the construction phase? The average is three to eight weeks from demolition to completion. Depending on the size of your bathroom and the scope of the work it needs, a full renovation could take nine to ten weeks or longer.
Suppose you have a small bathroom that doesn't need a new layout, updated electrical, or a custom vanity. In that case, upgrading the space could take as little as three to four weeks. Yet, if you intend to gut the room to fit in new plumbing, custom fixtures, and a new layout, it's reasonable to expect a longer project timeline.
How Long Do Different Bathroom Remodeling Stages Last?
If an average primary bath remodel can take several weeks, what are the general timelines for completing different tasks? The baseline timeframes for typical remodeling duties that occur during the construction phase include:
- Demolitions: In the first week, the workers will spend about half a day preparing the bathroom or job site. Afterward, the team will take up to one full day to tear down the old bathroom.
- Rough-in installations: The rough-in phase involves setting up all essential electrical, plumbing, and framing features behind the walls in the updated space. Adding extra circuits, installing new water lines, or setting up frames for new walls could take two to three days.
- Inspection: Bathroom inspections ensure that everything complies with Parma building codes. An inspector usually takes one day to assess the job site's structural, electrical, and plumbing changes.
- Finish carpentry: This is the stage where the team incorporates fine details into the bathroom to make it look more like a proper room rather than a construction zone. Preparations can take up to three days, drywall repair can take up to two days, and the shower pan installation and inspection take one day.
- Tile installation: It can take five to seven days to install new bathroom tile.

Start Your Bathroom Upgrade in Parma With Help From a Local Plumbing Contractor
How long does a bathroom remodel take? Depending on your project, it could take between five and nine weeks to complete. Working with an experienced plumbing contractor like Formica Plumbing & Sewer Co. can help you keep your project's timelines and budget without sacrificing the quality of the plumbing work.